What are our major issues...
Property tax clearing by HDIL. This has already been paid to HDIL/DTM as part of the CAM. This has been cleared for some shops in the form of credit noted when the shop owners have paid to MCGM directly. However there is an outstanding of over 18 crores due to MCGM as per their records.
Restoration of Common area electricity : HDIL has run up a outstanding to the tune of 1.8 crores in outstanding to MSEDCL. Without the common area electricity we cannot resore lifts, elcelators, pumps, lights in common areas, toilets etc. Currently the administrator is running some basic services on Diesel Generator.
Drinking Water in the mall has been stopped sometime in 2014 due to non payment of dues by HDIL. We are currently operating on TANKERS which is both expensive and unreliable.
Equal and fair contribution of all entities towards the upkeep of the mall.
Starting of Central Air Conditoining or in solving the problem of ventilation in the mall.
Closure of the company that has been taking the shop owners for a ride, and formation of a society to take care of the affairs of the mall.
|
01-Sep-09 |
Part OC received
(Basement, Lower Ground, Upper Ground, 1st and 2nd (PT) upper floor. |
|
20-Sep-09 |
Pre-Opening meeting for
MALL, few shops opened in Oct, Nov 2009. AC plant not started. |
|
01-Dec-09 |
HDIL Entertainment
(sister concern of HDIL, running multiplex) starts collecting CAM
(Common Maintenance charge) from Nov/Dec 2009 at Rs12/sqft of Super
Built up area. |
|
01-Jan-10 |
Started charging
Maintenance on the basis of sale area, Jan-Mar 2010 at 9 Rs /sqft as AC
is also not functional. |
|
01-Apr-10 |
AC testing started
between 2.0pm to 6.0pm within shops. Cam raised to 12 rs/sqft. People
protested. Said we were starting AC, and Anchor has been signed, and
would be operational in couple of months. |
|
01-Dec-10 |
CAM raised to 18/sqft,
told that this is due to property tax. Amended invoice to mention as per
clause 14 which mentions municipal taxes. |
|
30-Nov-12 |
Legal notice to HDIL,
Satra non-formation of society |
|
01-Jan-13 |
General Body approves
society formation |
|
30-Jan-13 |
Application for Shop
owners society formation |
|
05-Feb-13 |
Received permission from
Registrar, to open A/c in Bank, given 2 months to get 60% members. |
|
30-Apr-13 |
Society GBM, could not
contact all members. HDIL was directed to share the contact details of
owners, but stalled the handing over details. Time extension given to
get 60%. |
|
10-May-13 |
Registration of Dreams
The Mall company by HDIL behind the back of shop owners in a matter of a
week. NO PARTICIPATION of any shop owners. |
|
01-Jun-13 |
HDIL Writes to Asst.Reg
against society. Says company already formed and therefore society
should not be permitted. |
|
31-Jul-13 |
Meeting with HDIL
(Nikita, Wadhwan…) where they said that they are trying to start a
hospital and have taken over the maintenance of the mall. They walk out
when questioned about Old accounts and Property tax. Signatures taken in
the pretext of the meeting from shop owners. |
|
08-Aug-13 |
Society application
rejected. Grounds : 60% not raised within, and company has been formed
in the meanwhile. Decide to appeal against order. |
|
14-Aug-13 |
Society writes to ROC
against Dreams the Mall, for not presenting any accounts, and not
holding any meetings etc. |
|
05-Sep-13 |
HDIL Ent. getspermission
as a Franchisee for MSEDCL. HDIL has already taken 15000/-from each shop
owner for setting up infrastructure, and giving MSEDCLmeter, but have
not given one till date. Use electricity connection topressurize shop
owners. |
|
13-Nov-13 |
Shops received prop tax
bill received from BMC from April 2010 to March 31, 2014, based on
Capital value. Come to know that HDIL/HDIL entertainment has not made
any payment till date to MCGM though they have collected the same in
CAM. |
|
07-Jan-14 |
Achievement of over 60%
members of shops, affidavit submitted. |
|
03-Feb-14 |
Div. Jt. Reg passes order
dismissing appeal as company is in existence and says that 2 entities
cannot manage the same property. For society application to be passed
the company needs to be dissolved. |
|
01-Jun-14 |
Meeting with various
lawyers including Adv.Sampath to explain our case. Need to collect funds
to make any progress as litigation is time consuming and expensive. |
|
11-Nov-14 |
Name of HDIL
entertainment changed to Carnival Films Entertainment Pvt. Ltd. HDIL
appears to have leased Multiplex to carnival, and sold HDIL
entertainment to Carnival. |
|
16-Feb-15 |
Sarogi writ for
electricity. Company commits in court that they are clearing dues, and
will honor promise of connection. Agitation and no electricity and BHAND
in the mall for 5 days. HDIL gives written assurance on society
formation and property tax on letterhead.
HDIL starts winding down all services, and nearly stops all
housekeeping work except for the food court and multiplex floors.
Security nearly disappears. |
|
7-Apr-15 |
MSEDCL connection
received by many shop owners, but they have to make deposit payment
again to MSEDCL despite paying HDIL/Satra. |
|
13-Sep-15 |
HDIL holds discussion
with members and again promises time bound plan for clearing property
tax. Asks shop owners who have CAM pending to pay property tax directly,
submit proof and get credit for CAM payment. For other who have no
pending balance promises to clear property tax within 3 months. |
|
Aug-15 |
Conditions on mall have
deteriorated so much that society decides to run washrooms, housekeeping
etc. based on voluntary contributions from fewshop owners. |
|
15-Sep-15 |
Adv.Sarogi does not
appear incourt. Court warn of passing order and Adv.Sarogi does not
appear. Casefor society formation lost by default. |
|
01-Jul-16 |
Many months of partial
on/off of supply. Electricity supply is completely disconnected for
common areas because of non-payment. |
|
03-Sep-16 |
Distribution Franchisee
agreement of HDIL entertainment is terminated. |
|